This is the only Definition of Done of the Hub. A work package is done, and may merge, when every line below that applies to it is true; a line that does not apply is
marked “n/a” in the pull request with a reason. “Done” means verified: a commit hash and the output of the checks, otherwise the package is reported as “not verified”.
A project copies the list from templates/definition-of-done.md, cuts it down to checks it really runs, adds its own lines and removes none that applies at its tier.
Rules
Every package
- R1. The package MUST meet the Done criterion of its brief, with the evidence in the pull request: a test, a command and its output, or a screenshot
(
process.work-packages#R7). - R2. The gate script MUST pass locally and in CI, and it MUST be the same script (
quality.quality-release#R5,quality.quality-release#R6). A failing gate MUST NOT be bypassed (quality.quality-release#R7). - R3. The checks of the package MUST have been seen to fail before the change and to pass after it; a fixed defect MUST have a regression test at the lowest test level
that reproduces it (
process.work-packages#R5,quality.quality-release#R8). - R4. At the standard tier and above a verifier who did not build the package MUST have re-run the checks and passed the change (
process.work-packages#R8,mgmt.governance-tiers#R7,mgmt.governance-tiers#R8); at the lightweight tier the builder MUST have checked the change against this list and said so. - R5. The files changed MUST be those the brief allows; any other MUST be explained in the pull request.
- R6. The pull request title and the commits MUST follow Conventional Commits, and a breaking change MUST be marked (
config.conventional-commits#R3). - R7. The documentation MUST be updated: user documentation, the README, and an ADR when an architecture decision was made.
CHANGELOG.mdMUST have a line under Unreleased when users of a release will notice the change. - R8. There MUST be no secrets, no debug leftovers and no new warnings in the build or the logs. A new dependency MUST have a compatible licence, be maintained and have no known exploited vulnerability.
- R9. A decision that belongs to the owner MUST be listed in the pull request under “Owner decisions needed” and MUST NOT be merged as decided
(
mgmt.roles-and-decision-rights#R9). - R10. The package’s line MUST be in the project’s log: id, branch, commit, verdict and time against the estimate (
process.work-packages#R12).
A change to stored data or a live system
- R11. A change that can destroy or rewrite data MUST have a backup proved by restore before it, recorded with the change (
ops.backups#R4,ops.backups#R5), and the rollback MUST have been tried or its steps listed (quality.quality-release#R13).
The project’s own lines
- R12. A project MAY add lines for its product, for example an accessibility check of changed pages, a tested down step for a database migration or translations for every changed string. It MUST NOT remove a line above that applies at its tier.
Guidance
Run the list as a person would run a pre-flight check: the author goes down it before asking for a review, the verifier goes down it again with the evidence in hand, and a missing line is a finding, not a mood. The commonest gap is R3: a check that has never been seen to fail. The next is R1 reported as a sentence (“tested”) instead of a command and its output.
At the lightweight tier R4 is done by the builder against the list. That is a lighter check, not a missing one: the project still says that the list was gone through, and by whom.
The project’s own list (a copy of the template) is kept short; a list of thirty lines is read as none. When a defect escapes, change the list (process.work-packages#R13) rather
than telling people to be careful.
Explanation
Why one list. “Done” had several homes: a testing line in the project rules, a template, the quality playbook and the pull request template. Each said something a little different, so a reviewer could not tell which one a pull request was held to. This list is the single home; the others link to it. Why “verified”. The Agile Alliance describes the Definition of Done as the shared understanding of what it means for work to be complete. Making that checkable (a command, its output and a hash) keeps the understanding from depending on who is asked.
Examples
Good. WP-2 of a small UK shop: the pull request lists the nine applicable lines with evidence, marks R11 “n/a: the mail template holds no stored data”, names commit 3f9a1c2,
shows the red and then green run of bash tests/run.sh, and carries a verifier’s pass after one finding was fixed. The log line is written.
Bad. A pull request that says “tested, works”. There is no hash, no output, the gate was run before the last edit, the verifier is the same session in a new tab, and a dependency was added without a look at its licence. It is reported as done and merged; three days later the licence turns out to be incompatible.
Sources
- Agile Alliance, Definition of Done — Agile Alliance; the meaning of the term. Accessed 2026-11-21.
- GitHub Docs, About protected branches — CC BY 4.0; required status checks and reviews before a merge. Accessed 2026-11-21.
- Google Engineering Practices, What to look for in a code review — CC BY 3.0; tests belong with the change and must be able to fail. Accessed 2026-11-21.